NIAF 2 - Nigeria Infrastructure Advisory Facility Phase 2
Enhanced management of infrastructure development at the federal level and in selected states
Project budget:
£47,755,794
Project start/end date:
16/12/2009 - 31/12/2016
Sector group
Energy generation and supply
Project Reference:
201433
Budget spent to Date:
£24,222,782
Special conditions attached to funding? No
Principal sector
Energy policy and administrative management 30%
Project progress by time:
The project status is currently: Operational
Project Budget by Sector
Energy policy and administrative management: £14,206,738.00 Public finance management: £11,838,948.00 Other: £400,000.00 Bio-diversity: £2,367,789.75 Privatisation: £7,103,369.00 Transport policy and administrative management: £11,838,948.00 Energy policy and administrative management: £14,206,738.00 Public finance management: £11,838,948.00 Public finance management: £11,838,948.00 Other: £400,000.00 Bio-diversity: £2,367,789.75 Privatisation: £7,103,369.00 Privatisation: £7,103,369.00 Transport policy and administrative management: £11,838,948.00
Project Budget by Year






How the project is divided up (components)
NIAF 2 - Design - Nigeria Infrastructure Advisory Facility - Phase 2 (201433-101)
Component Budget by Sector
Energy policy and administrative management: £21,854.07 Public finance management: £18,211.72 Other: £0.00 Bio-diversity: £3,642.34 Privatisation: £10,927.04 Transport policy and administrative management: £18,211.72 Energy policy and administrative management: £21,854.07 Public finance management: £18,211.72 Public finance management: £18,211.72 Other: £0.00 Bio-diversity: £3,642.34 Privatisation: £10,927.04 Privatisation: £10,927.04 Transport policy and administrative management: £18,211.72
Component Budget by Year
Component Details
What it's for: Procurement of services
Country: Nigeria
Special conditions attached to funding? No
Start Date: 01/09/2010
End Date: 31/12/2016
Financial Information
DFID Financial YearApproved BudgetActual Spend To DateQ1 SpendQ2 SpendQ3 SpendQ4 Spend
2009/2010£0£0£0£0£0£0
2010/2011£70,898£70,898£0£0£676£3,622
2011/2012£1,949£1,949£997£32£1,011-£92
2012/2013£0£0£0£0£0£0
Aid Effectiveness
Aid To Government Sector
Is this contribution aid to the government sector? No
Use of partner country public financial management systems
Are partner country budget systems used? No
Are partner country financial reporting systems used? No
Are partner country audit systems used? No
Are all 3 partner country public financial management systems used? No
Are partner country procurement systems used? No
Use of programme based approaches
Does the contribution fit within a single programme/budget framework? No
Is the contribution led by the host country/organisation? No
Is there a process for co-ordinating donors? No
Are at least 2 partner country systems being used? No
Is this a Programme Based Approach? No
NIAF 2 - Implementation - Nigeria Infrastructure Advisory Facility - Procurement of Services (201433-102)
Component Budget by Sector
Energy policy and administrative management: £14,137,622.00 Public finance management: £11,781,352.00 Other: £0.00 Bio-diversity: £2,356,270.50 Privatisation: £7,068,811.00 Transport policy and administrative management: £11,781,352.00 Energy policy and administrative management: £14,137,622.00 Public finance management: £11,781,352.00 Public finance management: £11,781,352.00 Other: £0.00 Bio-diversity: £2,356,270.50 Privatisation: £7,068,811.00 Privatisation: £7,068,811.00 Transport policy and administrative management: £11,781,352.00
Component Budget by Year
Component Details
What it's for: Procurement of services
Country: Nigeria
Special conditions attached to funding? No
Start Date: 01/09/2010
End Date: 31/12/2016
Financial Information
DFID Financial YearApproved BudgetActual Spend To DateQ1 SpendQ2 SpendQ3 SpendQ4 Spend
2010/2011£0£0£0£0£0£0
2011/2012£4,645,200£4,645,200£0£0£0£4,270,200
2012/2013£21,644,780£21,726,170£1,765,649£7,421,416£5,495,373£7,043,734
2013/2014£10,801,490-£2,400,000-£2,400,000£0£0£0
2014/2015£9,620,681£0£0£0£0£0
2015/2016£413,256£0£0£0£0£0
2016/2017£0£0£0£0£0£0
Aid Effectiveness
Aid To Government Sector
Is this contribution aid to the government sector? No
Use of partner country public financial management systems
Are partner country budget systems used? No
Are partner country financial reporting systems used? No
Are partner country audit systems used? No
Are all 3 partner country public financial management systems used? No
Are partner country procurement systems used? No
Use of programme based approaches
Does the contribution fit within a single programme/budget framework? No
Is the contribution led by the host country/organisation? No
Is there a process for co-ordinating donors? No
Are at least 2 partner country systems being used? No
Is this a Programme Based Approach? No
NIAF 2 - Programme Funded Post - Infrastructure Adviser (201433-103)
Component Budget by Sector
Energy policy and administrative management: £47,262.19 Public finance management: £39,385.16 Other: £0.00 Bio-diversity: £7,877.03 Privatisation: £23,631.09 Transport policy and administrative management: £39,385.16 Energy policy and administrative management: £47,262.19 Public finance management: £39,385.16 Public finance management: £39,385.16 Other: £0.00 Bio-diversity: £7,877.03 Privatisation: £23,631.09 Privatisation: £23,631.09 Transport policy and administrative management: £39,385.16
Component Budget by Year
Component Details
What it's for: Procurement of services
Country: Nigeria
Special conditions attached to funding? No
Start Date: 16/12/2009
End Date: 31/12/2016
Financial Information
DFID Financial YearApproved BudgetActual Spend To DateQ1 SpendQ2 SpendQ3 SpendQ4 Spend
2011/2012£52,000£52,000£0£0£0£0
2012/2013£105,541£105,541£1,682,107-£1,596,987£20,421£0
Aid Effectiveness
Aid To Government Sector
Is this contribution aid to the government sector? --
Use of partner country public financial management systems
Are partner country budget systems used? --
Are partner country financial reporting systems used? --
Are partner country audit systems used? --
Are all 3 partner country public financial management systems used? No
Are partner country procurement systems used? --
Use of programme based approaches
Does the contribution fit within a single programme/budget framework? --
Is the contribution led by the host country/organisation? --
Is there a process for co-ordinating donors? --
Are at least 2 partner country systems being used? --
Is this a Programme Based Approach? No
NIAF 2- Monitoring & Evaluation - Nigeria Infrastructure Advisory Facility 2 (201433-104)
Component Budget by Sector
Budget information is not currently available for this component.
Component Budget by Year
Budget information is not currently available for this component.
Component Details
What it's for: Procurement of services
Country: Nigeria
Special conditions attached to funding? No
Start Date: 16/12/2009
End Date: 31/12/2016
Financial Information

This component of the project is in active procurement. In order to protect value for money we will publish financial information at a later stage.

Aid Effectiveness
Aid To Government Sector
Is this contribution aid to the government sector? No
Use of partner country public financial management systems
Are partner country budget systems used? --
Are partner country financial reporting systems used? --
Are partner country audit systems used? --
Are all 3 partner country public financial management systems used? No
Are partner country procurement systems used? --
Use of programme based approaches
Does the contribution fit within a single programme/budget framework? --
Is the contribution led by the host country/organisation? --
Is there a process for co-ordinating donors? --
Are at least 2 partner country systems being used? --
Is this a Programme Based Approach? No
NIAF 2 - Procurement of Goods - Nigeria Infrastructure Advisory Facility 2 (201433-105)
Component Budget by Sector
Rural development: £80,000.00 Road transport: £320,000.00 Road transport: £320,000.00 Rural development: £80,000.00 Rural development: £80,000.00 Road transport: £320,000.00 Road transport: £320,000.00
Component Budget by Year
Component Details
What it's for: Procurement of goods
Country: Nigeria
Special conditions attached to funding? No
Start Date: 05/02/2013
End Date: 31/12/2016
Financial Information
DFID Financial YearApproved BudgetActual Spend To DateQ1 SpendQ2 SpendQ3 SpendQ4 Spend
2013/2014£300,000£21,024£21,024£0£0£0
2014/2015£100,000£0£0£0£0£0
Aid Effectiveness
Aid To Government Sector
Is this contribution aid to the government sector? No
Use of partner country public financial management systems
Are partner country budget systems used? No
Are partner country financial reporting systems used? No
Are partner country audit systems used? No
Are all 3 partner country public financial management systems used? No
Are partner country procurement systems used? No
Use of programme based approaches
Does the contribution fit within a single programme/budget framework? No
Is the contribution led by the host country/organisation? No
Is there a process for co-ordinating donors? No
Are at least 2 partner country systems being used? No
Is this a Programme Based Approach? No